Oregon Statutes - Chapter 757 - Utility Regulation Generally - Section 757.660 - Use of arbitration to resolve disputes relating to valuation of electric company investments; rules.

(1) In adopting market valuation methodologies under ORS 757.659 (4), the Public Utility Commission may provide for use of arbitration to resolve disputes relating to valuation of electric company investments.

(2) The commission shall adopt rules for the following purposes:

(a) Establishing the process for selecting an arbitrator under this section.

(b) Establishing the type, scope and subject matter of arbitrations under this section, and the procedure for conducting those arbitrations.

(c) Establishing standards for the decision of an arbitrator under this section.

(d) Governing who may be a party to an arbitration under this section.

(3)(a) An arbitrator selected under rules adopted pursuant to subsection (2) of this section must be experienced in valuing generating resources and may not have any material conflict of interest in the result of the arbitration.

(b) Any party to the arbitration may challenge the selection of an arbitrator by direct petition to the commission. The commission’s review of the selection shall be limited to allegations of bias and lack of qualifications. The commission shall hold a hearing within 10 days after the filing of a petition, and the commission shall issue a final decision within 10 days after the hearing. The commission may require selection of a different arbitrator.

(4) The arbitrator shall control the time, manner and place of the arbitration, subject to any limitations established by commission rule.

(5) An arbitrator acts on behalf of the commission in performing duties and powers under this section and under rules adopted by the commission pursuant to this section. Nothing in this section shall be construed to grant any rights or privileges to an arbitrator that are otherwise afforded to persons employed by the state.

(6) The commission shall enforce an arbitration decision made pursuant to this section, unless any party to the arbitration files written exceptions with the commission for any of the following causes:

(a) The decision was procured by corruption, fraud or undue means;

(b) There was evident partiality or corruption on the part of the arbitrator;

(c) The arbitrator exceeded the arbitrator’s powers, or so imperfectly executed the arbitrator’s powers that the rights of the party were substantially prejudiced;

(d) There was an evident material miscalculation of figures or an evident material mistake in the description of any thing or property referred to in the decision; or

(e) The decision was based on an erroneous interpretation of a statute, rule or other law.

(7) If, after a hearing on the exceptions filed as provided in subsection (6) of this section, it appears to the commission that the decision should be set aside or modified, the commission may by order refer the decision back to the arbitrator with proper instructions for correction or rehearing.

(8) A commission order or decision under this section may not be appealed until after the commission issues a final order adopting the arbitration decision. [2001 c.134 §1a; 2005 c.22 §507; 2005 c.638 §10]

Note: 757.660 was added to and made a part of 757.600 to 757.689 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

Section:  Previous  757.649  757.650  757.652  757.654  757.655  757.656  757.659  757.660  757.661  757.663  757.665  757.667  757.669  757.670  757.672  Next

Last modified: August 7, 2008