Arizona Revised Statutes § 28-6924 Progress Payments

28-6924. Progress payments

A. The following apply to the department's highway construction projects awarded pursuant to section 28-6923, 28-7365 or 28-7366:

1. Progress payments may be made by the department to the contractor on the basis of a duly certified and approved estimate of the work performed during a preceding period of time. The progress payments shall be paid on or before fourteen days after the estimate of the work is certified and approved. The estimate of the work shall be deemed received by the department on submission to the person designated by the department for the submission, review or approval of the estimate of the work. An estimate of the work submitted under this section shall be deemed approved and certified after seven days from the date of submission unless before that time the department prepares and issues a specific written finding detailing those items in the estimate of the work that are not approved and certified under the contract. The department may withhold an amount from the progress payment sufficient to pay the expenses the department reasonably expects to incur in correcting the deficiency set forth in the written finding. On completion and acceptance of separate divisions of the contract on which the price is stated separately in the contract, payment may be made in full including retained percentages, less deductions, unless a substitute security has been provided.

2. The contractor shall pay to the contractor's subcontractors or material suppliers and each subcontractor shall pay to the subcontractor's subcontractors or material suppliers, within seven days of receipt of each progress payment, unless otherwise agreed in writing by the parties, the respective amounts allowed the contractor or subcontractor on account of the work performed by the contractor's or subcontractor's subcontractors or material suppliers, to the extent of each subcontractor's or material supplier's interest in the amount. These payments to subcontractors or material suppliers shall be based on payments received pursuant to this section. Any diversion by the contractor or subcontractor of payment received for work performed on a contract or failure to reasonably account for the application or use of the payments constitutes grounds for disciplinary action by the registrar of contractors. A subcontractor or material supplier shall notify the registrar of contractors and the department in writing of any payment less than the amount of percentage approved for the class or item of work as set forth in this section.

3. A subcontractor may notify the department in writing requesting that the subcontractor be notified by the department in writing within five days after payment of each progress payment made to the contractor. The subcontractor's request under this paragraph remains in effect for the duration of the subcontractor's work on the project.

4. If any payment to a contractor is delayed after the date due, interest shall be paid at the rate of one per cent per month or a fraction of the month on the unpaid balance.

5. If any periodic or final payment to a subcontractor or material supplier is delayed by more than seven days after receipt of the periodic or final payment by the contractor or subcontractor, the contractor or subcontractor shall pay the subcontractor or material supplier interest, beginning on the eighth day, at the rate of one per cent per month or a fraction of a month on the unpaid balance.

B. A contract for construction shall not materially alter the rights of any contractor, subcontractor or material supplier to receive prompt and timely payment as provided under this section.

C. Nothing in this section prevents a contractor or subcontractor, at the time of application and certification to the department or contractor, from withholding the application and certification to the department or contractor for payment to the subcontractor or material supplier for unsatisfactory job progress, defective construction work or materials not remedied, disputed work or materials, third party claims filed or reasonable evidence that a claim will be filed, failure of a subcontractor to make timely payments for labor, equipment and materials, damage to the contractor or another subcontractor, reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract amount or a reasonable amount for retention that does not exceed the annual percentage retained by the department.

D. This section creates no duty of the department to a subcontractor or material supplier other than the duty to notify pursuant to subsection A, paragraph 3 of this section and creates no cause of action in favor of a subcontractor or material supplier against this state, the department or any state employee or agent.

Section: Previous  28-6806  28-6807  28-6808  28-6901  28-6921  28-6922  28-6923  28-6924  28-6925  28-6926  28-6951  28-6952  28-6953  28-6954  28-6955  Next

Last modified: October 13, 2016