45-160. Limitation on time of completion of construction; exception

Actual construction, except under applications by a city or town for municipal uses, shall begin within two years after approval of the application, and shall be prosecuted with reasonable diligence and completed within a reasonable time which shall be fixed in the permit at not to exceed five years from the date of approval. The director shall, for good cause shown, extend the time beyond the five-year period if the magnitude, physical difficulties and cost of the work justify extension.

Section: Previous  45-153  45-154  45-155  45-156  45-157  45-158  45-159  45-160  45-161  45-162  45-163  45-164  45-165  45-166  45-171  Next