California Civil Code Section 9566

CA Civ Code § 9566 (2017)  

(a) A claimant does not have a right to recover on a payment bond unless the claimant provided work to the direct contractor either directly or through one or more subcontractors pursuant to a public works contract.

(b) Nothing in this section affects the stop payment notice rights of, and relative priorities among, design professionals.

(Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)