378.405 Reclamation review procedure.—
(1) All agency reviews conducted under this part are subject to this section. Within 30 days after receipt of an operator’s conceptual reclamation plan, the department, the secretary, or the affected agency shall review the plan and shall request submittal of all additional information the agency is permitted by law to require. If the applicant believes any agency request for additional information is not authorized by law or agency rule, the applicant may request a hearing under ss. 120.569 and 120.57. Within 30 days after receipt of such additional information, the agency must review it and may request only such further information as is needed to clarify the additional information.
(2) If the applicant believes the request of the agency for such additional information is not authorized by law or agency rule, the agency, at the applicant’s request, shall proceed to process the plan. A plan must be approved or denied within 90 days after receipt of the original plan, the last item of timely requested additional information, or the applicant’s written request to begin processing the plan.
History.—s. 1, ch. 86-294; ss. 326, 510, ch. 94-356; s. 111, ch. 96-410.
Section: Previous 378.401 378.402 378.403 378.404 378.405 378.406 378.407 378.408 378.409 378.411 378.4115 378.412 378.501 378.502 378.503 NextLast modified: September 23, 2016