[§196-1.5 Priority permitting process for renewable energy projects.] All agencies shall provide priority handling and processing for all state permits required for renewable energy projects.

For purposes of this section, "agencies" means any executive department, independent commission, board, bureau, office, or other establishment of the State, or any quasi-public institution that is supported in whole or in part by state funds. [L 2007, c 205, §3]

Cross References

For similar provisions, see §§46-19.4 and 226-18(c)(10).