General Laws of Massachusetts - Chapter 43D Expedited Permitting - Section 8 Grounds for denial of grant

Section 8. The grant shall not occur where: (1) the governing body has made a timely determination that the application is not complete in accordance with its requirements and notified the applicant as set forth herein and the applicant has not made a timely response to complete the application; (2) the governing body has determined that the final application contained false or misleading information; or (3) the governing body has determined that substantial changes to the project affect the information required to process the permit application have occurred since the filing of the application.