Michigan Compiled Laws § 125.1593 Contract Completion; Performance; Consent Of Governmental Entity; Arbitration; Judgment Rendered.


125.1593 Contract completion; performance; consent of governmental entity; arbitration; judgment rendered.

Sec. 3.

(1) If the contractor does not agree with the governmental entity's determination, with the governmental entity's consent the contractor may complete performance on the contract.

(2) At the option of the governmental entity, the contractor and the governmental entity shall arbitrate the contractor's entitlement to recover the actual increase in contract time and costs incurred because of the physical condition of the improvement site. The arbitration shall be conducted in accordance with the rules of the American arbitration association and judgment rendered may be entered in any court having jurisdiction.


History: 1998, Act 57, Eff. Oct. 6, 1998


Section: Previous  125.1591  125.1592  125.1593  125.1594  125.1595  125.1596    Next