Nevada Revised Statutes Section 704.891 - Energy - Public Utilities

Reports to be filed with Commission by person holding permit who is not public utility.

1. Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900, inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:

(a) The location, nature and capacity of that facility;

(b) The anticipated date for commercial operation of that facility;

(c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and

(d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.

2. The reports required by subsection 1 must be filed:

(a) On or before the date on which construction of a utility facility is commenced; and

(b) On a date not later than:

(1) Twelve months before the scheduled date of commercial operation of that facility; or

(2) Thirty days before the actual date of commercial operation of that facility,

Ê whichever is earlier.

Last modified: February 26, 2006