North Carolina General Statutes § 62-182 Acquisition of right-of-way by contract

Such telegraph, telephone, or electric power or lighting company has power to contract with any person or corporation, the owner of any lands or of any franchise or easement therein, over which its lines are proposed to be erected, for the right-of-way for planting, repairing and preservation of its poles or other property, and for the erection and occupation of offices at suitable distances for the public accommodation. This section shall not be construed as requiring electric power or lighting companies to erect offices for public accommodation. (1874-5, c. 203, s. 3; Code, s. 2008; 1899, c. 64; 1903, c. 562, ss. 1, 2; Rev., s. 1572; C.S., s. 1697; 1963, c. 1165, s. 1.)

Sections:  Previous  62-167  62-168  62-169  62-170  62-171  62-180  62-181  62-182  62-182.1  62-183  62-184  62-185  62-187  62-189  62-190  Next