Oregon Statutes - Chapter 215 - County Planning; Zoning; Housing Codes - Section 215.427 - Final action on permit or zone change application; refund of application fees.

(1) Except as provided in subsections (3) and (5) of this section, for land within an urban growth boundary and applications for mineral aggregate extraction, the governing body of a county or its designee shall take final action on an application for a permit, limited land use decision or zone change, including resolution of all appeals under ORS 215.422, within 120 days after the application is deemed complete. The governing body of a county or its designee shall take final action on all other applications for a permit, limited land use decision or zone change, including resolution of all appeals under ORS 215.422, within 150 days after the application is deemed complete, except as provided in subsections (3) and (5) of this section.

(2) If an application for a permit, limited land use decision or zone change is incomplete, the governing body or its designee shall notify the applicant in writing of exactly what information is missing within 30 days of receipt of the application and allow the applicant to submit the missing information. The application shall be deemed complete for the purpose of subsection (1) of this section upon receipt by the governing body or its designee of:

(a) All of the missing information;

(b) Some of the missing information and written notice from the applicant that no other information will be provided; or

(c) Written notice from the applicant that none of the missing information will be provided.

(3)(a) If the application was complete when first submitted or the applicant submits additional information, as described in subsection (2) of this section, within 180 days of the date the application was first submitted and the county has a comprehensive plan and land use regulations acknowledged under ORS 197.251, approval or denial of the application shall be based upon the standards and criteria that were applicable at the time the application was first submitted.

(b) If the application is for industrial or traded sector development of a site identified under section 12, chapter 800, Oregon Laws 2003, and proposes an amendment to the comprehensive plan, approval or denial of the application must be based upon the standards and criteria that were applicable at the time the application was first submitted, provided the application complies with paragraph (a) of this subsection.

(4) On the 181st day after first being submitted, the application is void if the applicant has been notified of the missing information as required under subsection (2) of this section and has not submitted:

(a) All of the missing information;

(b) Some of the missing information and written notice that no other information will be provided; or

(c) Written notice that none of the missing information will be provided.

(5) The period set in subsection (1) of this section may be extended for a specified period of time at the written request of the applicant. The total of all extensions may not exceed 215 days.

(6) The period set in subsection (1) of this section applies:

(a) Only to decisions wholly within the authority and control of the governing body of the county; and

(b) Unless the parties have agreed to mediation as described in ORS 197.319 (2)(b).

(7) Notwithstanding subsection (6) of this section, the period set in subsection (1) of this section does not apply to an amendment to an acknowledged comprehensive plan or land use regulation or adoption of a new land use regulation that was forwarded to the Director of the Department of Land Conservation and Development under ORS 197.610 (1).

(8) Except when an applicant requests an extension under subsection (5) of this section, if the governing body of the county or its designee does not take final action on an application for a permit, limited land use decision or zone change within 120 days or 150 days, as applicable, after the application is deemed complete, the county shall refund to the applicant either the unexpended portion of any application fees or deposits previously paid or 50 percent of the total amount of such fees or deposits, whichever is greater. The applicant is not liable for additional governmental fees incurred subsequent to the payment of such fees or deposits. However, the applicant is responsible for the costs of providing sufficient additional information to address relevant issues identified in the consideration of the application.

(9) A county may not compel an applicant to waive the period set in subsection (1) of this section or to waive the provisions of subsection (8) of this section or ORS 215.429 as a condition for taking any action on an application for a permit, limited land use decision or zone change except when such applications are filed concurrently and considered jointly with a plan amendment. [1997 c.414 §2; 1999 c.393 §§3,3a; enacted in lieu of 215.428 in 1999; 2003 c.800 §30; 2007 c.232 §1]

Section:  Previous  215.415  215.416  215.417  215.418  215.420  215.422  215.425  215.427  215.428  215.429  215.430  215.431  215.433  215.435  215.437  Next

Last modified: August 7, 2008