Oregon Statutes - Chapter 279C - Public Contracting - Public Improvements and Related Contracts - Section 279C.655 - Extension and compensation when work suspended.

If a public contract is not terminated but work under the contract is suspended by an order of a contracting agency for any reason considered to be in the public interest other than a labor dispute or any third-party judicial proceeding relating to the work other than a suit or action filed in regards to a labor dispute, the contractor is entitled to a reasonable extension of the contract time and reasonable compensation for all costs resulting from the suspension plus a reasonable allowance for overhead with respect to such costs. [2003 c.794 §161]