Oregon Statutes - Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects - Section 543A.135 - Exceptions to final order.

(1) Within 20 days after the Water Resources Director issues a final order under ORS 543A.130 after the conclusion of a contested case hearing, any party may file exceptions to the order with the Water Resources Commission.

(2) The commission shall issue a modified order, if the exceptions are allowed, or deny the exceptions within 60 days after the close of the exception period under subsection (1) of this section. [1997 c.449 §26]

Section:  Previous  543A.100  543A.105  543A.110  543A.115  543A.120  543A.125  543A.130  543A.135  543A.140  543A.145  543A.150  543A.300  543A.305  543A.400  543A.405  Next