Texas Local Government Code § 271.060 Change Orders

Sec. 271.060. CHANGE ORDERS. (a) After performance of a construction contract begins, a governing body may approve change orders if necessary to:

(1) make changes in plans or specifications; or

(2) decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be furnished.

(b) The total price of a contract may not be increased by a change order unless provision has been made for the payment of the added cost by the appropriation of current funds or bond funds for that purpose, by the authorization of the issuance of certificates, or by a combination of those procedures.

(c) A contract with an original contract price of $1 million or more may not be increased by more than 25 percent. If a change order for a contract with an original contract price of less than $1 million increases the contract amount to $1 million or more, subsequent change orders may not increase the revised contract amount by more than 25 percent.

(d) A governing body may grant authority to an official or employee responsible for purchasing or for administering a contract to approve a change order that involves an increase or decrease of $50,000 or less.

Acts 1987, 70th Leg., ch. 149, Sec. 1, eff. Sept. 1, 1987.

Amended by:

Acts 2011, 82nd Leg., R.S., Ch. 479 (H.B. 679), Sec. 2, eff. June 17, 2011.

Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 2.11, eff. September 1, 2011.

Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.001(34), eff. September 1, 2013.

Section: Previous  271.054  271.055  271.056  271.0565  271.057  271.058  271.059  271.060  271.061  271.062  271.063  271.064  271.081  271.082  271.083  Next

Last modified: September 28, 2016