Texas Utilities Code § 121.2025 Authority Of Municipality To Assess Charges

Sec. 121.2025. AUTHORITY OF MUNICIPALITY TO ASSESS CHARGES. (a) Except as otherwise provided by this section or Section 182.025, Tax Code, a municipality may not assess a charge for the placement, construction, maintenance, repair, replacement, operation, use, relocation, or removal of a gas pipeline facility on, along, under, or across a public road, highway, street, alley, stream, canal, or other public way.

(b) A municipality may:

(1) assess a reasonable annual charge for the placement, construction, maintenance, repair, replacement, operation, use, relocation, or removal by an owner or operator of a gas pipeline facility on, along, or across the public roads, highways, streets, alleys, streams, canals, or other public ways located within the municipality and maintained by the municipality; and

(2) recover the reasonable cost of repairing damage to a public road, highway, street, alley, stream, canal, or other public way located within the municipality and maintained by the municipality that is caused by the placement, construction, maintenance, repair, replacement, operation, use, relocation, or removal of a gas pipeline facility if the owner or operator of the facility does not repair the damage in accordance with generally applicable paving standards or other applicable standards in the municipality.

(c) A charge authorized by Subsection (b)(1) may not exceed the cost to the municipality of administering, supervising, inspecting, and otherwise regulating the location of the gas pipeline facility, including maintaining records and maps of the location of the pipeline facility.

(d) The owner or operator of a gas pipeline facility may appeal the assessment of a charge under Subsection (b)(1) to the railroad commission. The railroad commission shall hear the appeal de novo. Unless the municipality that assessed the charge establishes that the charge is authorized by this section, the railroad commission shall declare the charge invalid or reduce the charge to an amount authorized by this section. The railroad commission has exclusive jurisdiction to determine whether a charge under Subsection (b)(1) is authorized by this section. The owner or operator of the gas pipeline facility and the municipality shall share equally the costs incurred by the railroad commission in connection with the appeal.

(e) A municipality must file suit to collect a charge authorized by Subsection (b)(1) not later than the fourth anniversary of the date the charge becomes due. The running of the limitations period under this subsection is tolled on the filing of an appeal of the charge under Subsection (d) and begins running again on the date the appeal is determined.

(f) This section may not be construed to prevent a municipality from:

(1) recovering the reasonable cost of repairing damage to a municipal facility, other than a public way, caused by acts of the owner or operator of a gas pipeline facility; or

(2) requiring the owner or operator of a gas pipeline facility to relocate the pipeline facility, at the owner's or operator's expense, to permit the construction, maintenance, modification, or alteration of a municipal facility.

(g) Notwithstanding Subsection (f)(2), the municipality shall pay the cost of relocating a gas pipeline facility if the pipeline facility is authorized by a property right that has priority over the municipality's right to use the public way for the municipal facility.

Added by Acts 2005, 79th Leg., Ch. 530 (H.B. 951), Sec. 6, eff. June 17, 2005.

Added by Acts 2005, 79th Leg., Ch. 720 (S.B. 480), Sec. 4, eff. September 1, 2005.

Amended by:

Acts 2009, 81st Leg., R.S., Ch. 1311 (H.B. 2572), Sec. 1, eff. June 19, 2009.

Section: Previous  121.154  121.155  121.157  121.158  121.201  121.2015  121.202  121.2025  121.203  121.204  121.205  121.206  121.207  121.208  121.209  Next