Sec. 36.454. PERMITTING, SPACING, AND PRODUCTION REQUIREMENTS. (a) Except as provided by Subsection (b), a district may not require a permit for the drilling, equipping, operation, or completion of an ASR injection well or an ASR recovery well that is authorized by the commission.

(b) The ASR recovery wells that are associated with an aquifer storage and recovery project are subject to the permitting, spacing, and production requirements of the district if the amount of groundwater recovered from the wells exceeds the volume authorized by the commission to be recovered under the project. The requirements of the district apply only to the portion of the volume of groundwater recovered from the ASR recovery wells that exceeds the volume authorized by the commission to be recovered.

(c) A project operator may not recover groundwater by an aquifer storage and recovery project in an amount that exceeds the volume authorized by the commission to be recovered under the project unless the project operator complies with the applicable requirements of a district as described by this section.

Added by Acts 2015, 84th Leg., R.S., Ch. 505 (H.B. 655), Sec. 4, eff. June 16, 2015.

Section: Previous  36.412  36.413  36.414  36.415  36.416  36.4165  36.417  36.418  36.419  36.451  36.452  36.453  36.454  36.455  36.456  Next

Last modified: September 28, 2016