15 USC 7307 - National Construction Safety Team Report

Not later than 90 days after completing an investigation, a Team shall issue a public report which includes—

(1) an analysis of the likely technical cause or causes of the building failure investigated;

(2) any technical recommendations for changes to or the establishment of evacuation and emergency response procedures;

(3) any recommended specific improvements to building standards, codes, and practices; and

(4) recommendations for research and other appropriate actions needed to help prevent future building failures.

(Pub. L. 107–231, §8, Oct. 1, 2002, 116 Stat. 1475.)