§ 18.27.114. Disclosure statement required -- Prerequisite to lien claim
(1) Any contractor agreeing to perform any contracting project: (a) For the repair, alteration, or construction of four or fewer residential units or accessory structures on such residential property when the bid or contract price totals one thousand dollars or more; or (b) for the repair, alteration, or construction of a commercial building when the bid or contract price totals one thousand dollars or more but less than sixty thousand dollars, must provide the customer with the following disclosure statement in substantially the following form using lower case and upper case twelve-point and bold type where appropriate, prior to starting work on the project:
This contractor is registered with the state of Washington, registration no. . . ., and has posted with the state a bond or deposit of . . . . . for the purpose of satisfying claims against the contractor for breach of contract including negligent or improper work in the conduct of the contractor's business. The expiration date of this contractor's registration is . . . . ..
THIS BOND OR DEPOSIT MIGHT NOT BE SUFFICIENT TO COVER A CLAIM THAT MIGHT ARISE FROM THE WORK DONE UNDER YOUR CONTRACT.
This bond or deposit is not for your exclusive use because it covers all work performed by this contractor. The bond or deposit is intended to pay valid claims up to . . . . . that you and other customers, suppliers, subcontractors, or taxing authorities may have.
FOR GREATER PROTECTION YOU MAY WITHHOLD A PERCENTAGE OF YOUR CONTRACT.
You may withhold a contractually defined percentage of your construction contract as retainage for a stated period of time to provide protection to you and help insure that your project will be completed as required by your contract.
YOUR PROPERTY MAY BE LIENED.
If a supplier of materials used in your construction project or an employee or subcontractor of your contractor or subcontractors is not paid, your property may be liened to force payment and you could pay twice for the same work.
FOR ADDITIONAL PROTECTION, YOU MAY REQUEST THE CONTRACTOR TO PROVIDE YOU WITH ORIGINAL "LIEN RELEASE" DOCUMENTS FROM EACH SUPPLIER OR SUBCONTRACTOR ON YOUR PROJECT.
The contractor is required to provide you with further information about lien release documents if you request it. General information is also available from the state Department of Labor and Industries.
I have received a copy of this disclosure statement.
. . . . . . . . . . . . . . . . . .
(Signature of customer)"
[2007 c 436 § 8; 2001 c 159 § 9; 1997 c 314 § 12; 1988 c 182 § 1; 1987 c 419 § 1.]
Notes:
Voluntary compliance with notification requirements: "Nothing in RCW 18.27.114 shall be construed to prohibit a contractor from voluntarily complying with the notification requirements of that section which take effect July 1, 1989, prior to that date." [1988 c 182 § 2.]
Sections: Previous 18.27.080 18.27.090 18.27.100 18.27.102 18.27.104 18.27.110 18.27.111 18.27.114 18.27.117 18.27.120 18.27.125 18.27.130 18.27.140 18.27.200 18.27.205 Next