Revised Code of Washington - RCW Title 35 Cities And Towns - Section 35.67.230 Sewerage lien foreclosure -- Limitation on time of commencement

§ 35.67.230. Sewerage lien foreclosure -- Limitation on time of commencement

An action to foreclose a sewerage lien pursuant to a lien notice filed as required by law must be commenced within two years from the date of the filing thereof.

An action to foreclose a six months' lien may be commenced at any time after six months subsequent to the furnishing of the sewerage service for which payment has not been made.

[1965 c 7 § 35.67.230. Prior: 1941 c 193 § 7, part; Rem. Supp. 1941 § 9354-10, part.]

Sections:  Previous  35.67.180  35.67.190  35.67.194  35.67.200  35.67.210  35.67.215  35.67.220  35.67.230  35.67.240  35.67.250  35.67.260  35.67.270  35.67.280  35.67.290  35.67.300  Next

Last modified: April 7, 2009