Oregon Statutes - Chapter 517 - Mining and Mining Claims - Section 517.984 - Modification of permit; project coordinating committee.

(1) The operator, the State Department of Geology and Mineral Industries, any other permitting agency or a cooperating agency may request modification of a permit issued under the process established under ORS 517.952 to 517.989.

(2) If a permitting agency is requested to make a permit modification that the permitting agency or a cooperating agency finds is a significant permit modification under the provisions of ORS 517.952 to 517.989, the agency shall notify the State Department of Geology and Mineral Industries. The department shall coordinate the organization of a project coordinating committee. The project coordinating committee shall review the proposed modification and determine those portions of ORS 517.952 to 517.989 with which the applicant must comply. The decision of the project review committee shall be:

(a) Limited to those portions of the chemical process mine operation to be modified; and

(b) Consistent with public participation as set forth in ORS 517.952 to 517.989. [1991 c.735 §22; 2007 c.318 §26]

Section:  Previous  517.977  517.978  517.979  517.980  517.981  517.982  517.983  517.984  517.985  517.986  517.987  517.988  517.989  517.990  517.992  Next

Last modified: August 7, 2008