Oregon Statutes - Chapter 517 - Mining and Mining Claims - Section 517.986 - Time limit for final action on permit subject to consolidated application process.

Notwithstanding any other provision of law, the State Department of Geology and Mineral Industries and any other permitting agency shall take final action to issue or deny a permit subject to the consolidated application process set forth in ORS 517.952 to 517.989 within one year after issuance of a notice to proceed under ORS 517.977. However, with the concurrence of the applicant, the processing of the application may be suspended for a period of time to allow the applicant to resolve issues having a bearing on, or necessary to any permitting agency’s decision or the department’s decision on whether to issue or deny a permit. [1991 c.735 §24]

Section:  Previous  517.977  517.978  517.979  517.980  517.981  517.982  517.983  517.984  517.985  517.986  517.987  517.988  517.989  517.990  517.992  Next

Last modified: August 7, 2008