Oregon Statutes - Chapter 758 - Utility Rights of Way and Territory Allocation; Cogeneration - Section 758.415 - Enforceability of contract approved by commission; conditions for approval.

Notwithstanding any other provisions of law, a contract entered into pursuant to ORS 758.410, when approved by the Public Utility Commission as provided in ORS 758.420 to 758.475, shall be valid and enforceable; provided, that the commission shall approve such a contract only if the commission finds, after a hearing as provided in ORS 758.420 to 758.475, that the contract will eliminate or avoid unnecessary duplicating facilities, and will promote the efficient and economic use and development and the safety of operation of the utility systems of the parties to the contract, while providing adequate and reasonable service to all territories and customers affected thereby. [Formerly 757.620]

Section:  Previous  758.305  758.310  758.315  758.320  758.400  758.405  758.410  758.415  758.420  758.425  758.430  758.435  758.440  758.445  758.450  Next