Texas Health And Safety Code § 382.059 Hearing And Decision On Permit Amendment Application Of Certain Electric Generating Facilities

Sec. 382.059. HEARING AND DECISION ON PERMIT AMENDMENT APPLICATION OF CERTAIN ELECTRIC GENERATING FACILITIES. (a) This section applies to a permit amendment application submitted solely to allow an electric generating facility to reduce emissions and comply with a requirement imposed by Section 112 of the federal Clean Air Act (42 U.S.C. Section 7412) to use applicable maximum achievable control technology. A permit amendment application shall include a condition that the applicant is required to complete the actions needed for compliance by the time allowed under Section 112 of the federal Clean Air Act (42 U.S.C. Section 7412).

(b) The commission shall provide an opportunity for a public hearing and the submission of public comment on the application in the manner provided by Section 382.0561.

(c) Not later than the 45th day after the date the application is received, the executive director shall issue a draft permit.

(d) Not later than the 30th day after the date of issuance of the draft permit under Subsection (c), parties may submit to the commission any legitimate issues of material fact regarding whether the choice of technology approved in the draft permit is the maximum achievable control technology required under Section 112 of the federal Clean Air Act (42 U.S.C. Section 7412) and may request a contested case hearing before the commission. If a party requests a contested case hearing under this subsection, the commission shall conduct a contested case hearing and issue a final order issuing or denying the permit amendment not later than the 120th day after the date of issuance of the draft permit under Subsection (c).

(e) The commission shall send notice of a decision on an application for a permit amendment under this section in the manner provided by Section 382.0562.

(f) A person affected by a decision of the commission to issue or deny a permit amendment may move for rehearing and is entitled to judicial review under Section 382.032.

(g) This section expires on the sixth anniversary of the date the administrator adopts standards for existing electric generating facilities under Section 112 of the federal Clean Air Act (42 U.S.C. Section 7412), unless a stay of the rules is granted.

(h) The commission shall adopt rules to implement this section.

Added by Acts 2011, 82nd Leg., R.S., Ch. 1021 (H.B. 2694), Sec. 4.27, eff. September 1, 2011.

Section: Previous  382.0563  382.0564  382.0565  382.0566  382.0567  382.057  382.058  382.059  382.0591  382.061  382.062  382.0621  382.0622  382.063  382.064  Next

Last modified: September 28, 2016