Revised Code of Washington - RCW Title 74 Public Assistance - Section 74.46.290 Expense for construction interest

§ 74.46.290. Expense for construction interest

(1) Interest expense and loan origination fees relating to construction of a facility incurred during the period of construction shall be capitalized and amortized over the life of the facility pursuant to RCW 74.46.360. The period of construction shall extend from the date of the construction loan to the date the facility is put into service for patient care.

(2) For the purposes of this chapter, the period provided for in subsection (1) of this section shall not exceed the project certificate of need time period pursuant to RCW 70.38.125.

[1980 c 177 § 29.]

Sections:  Previous  74.46.200  74.46.220  74.46.230  74.46.240  74.46.250  74.46.270  74.46.280  74.46.290  74.46.300  74.46.310  74.46.320  74.46.330  74.46.340  74.46.350  74.46.360  Next

Last modified: April 7, 2009