Alaska Statutes Title 09, Chapter 09.45, Article 11 - Action for Dwelling Design, Construction, or Remodeling Claims
- Sec. 09.45.881 Notice of Claim.
(a) In an action brought on a claim against a construction professional, the claimant shall, at least 90 days before filing the action, serve...
- Sec. 09.45.882 Written Response to Notice of Claim.
(a) Within 21 days after service of the notice under AS 09.45.881, the construction professional shall serve a written response on the claimant.(b) The...
- Sec. 09.45.883 Court Action Allowed If Claim Disputed or Not Responded To.
If the construction professional disputes the claim in the notice under AS 09.45.882 (b)(3) or does not respond to the claimant's notice of claim...
- Sec. 09.45.884 Consequence of Rejecting Inspection or Settlement Offer.
(a) If the claimant rejects the inspection offer under AS 09.45.882(b)(1) or the settlement offer under AS 09.45.882 (b)(2), the claimant shall serve written...
- Sec. 09.45.885 Consequence of Accepting Inspection Offer.
If a claimant elects to allow the construction professional to make an inspection under AS 09.45.882 (b)(1), the claimant shall provide the construction professional...
- Sec. 09.45.886 Procedure After Inspection.
Within 14 days after completion of an inspection made under AS 09.45.885, the construction professional shall serve on the claimant a written(1) offer to...
- Sec. 09.45.887 Court Action Allowed After Failure to Repair or to Settle.
If the construction professional does not respond within the time required by AS 09.45.886 , does not repair the defect to the satisfaction of...
- Sec. 09.45.888 Court Action Allowed If Claimant Rejects Offer.
(a) If the claimant rejects an offer made by the construction professional under AS 09.45.886 (1) or (2), the claimant shall serve written notice...
- Sec. 09.45.889 Unreasonable Rejection of Offer.
(a) If a claimant unreasonably rejects an offer made under AS 09.45.881 - 09.45.899 or does not give the construction professional a reasonable opportunity...
- Sec. 09.45.890 Acceptance of Offer.
(a) To accept an offer of a construction professional to repair a defect under AS 09.45.886 (1), a claimant shall serve the construction professional...
- Sec. 09.45.891 Presumption of Mitigation.
If a claimant fails to allow a construction professional to make a reasonable inspection requested by the construction professional under AS 09.45.882 (b)(1), or...
- Sec. 09.45.892 Noncompliance Assertion Prohibited.
Unless there is good cause for the failure, a construction professional may not assert that the claimant did not comply with AS 09.45.881 -...
- Sec. 09.45.893 Notice Required in Contract.
(a) In order to take advantage of any rights of a construction professional under AS 09.45.881 - 09.45.899, when a construction professional enters into...
- Sec. 09.45.894 Additional Construction Defects; Additional Notice of Claim Required.
A court action for a defect that is discovered after a claimant has provided a construction professional with a notice of claim required in...
- Sec. 09.45.895 Limitation on Damages; Collateral Sources.
(a) Except as provided in (c) of this section, in an action covered under AS 09.45.881 - 09.45.899, a claimant may recover only the...
- Sec. 09.45.896 Exemption.
AS 09.45.881 - 09.45.899 do not apply to claims for personal injury, including death.
- Sec. 09.45.899 Definitions.
In AS 09.45.881 - 09.45.899,(1) "action" means a civil action or an arbitration proceeding for damages or indemnification;(2) "claim" means a claim against a...