27-1252. Notice of complete, incomplete or denied plan
A. The state mine inspector shall notify the operator that a reclamation plan is administratively complete or incomplete within thirty days after receiving the plan.
B. If the inspector notifies the operator that a plan is incomplete or denied, the inspector shall include a written explanation stating the reasons for denial including recommendations for correcting incomplete or unacceptable parts of the plan consistent with the requirements of this chapter. The operator must refile the corrected plan within ninety days after notification that the previous plan was incomplete or denied or within a time frame mutually agreed on between the operator and the state mine inspector that would not materially affect the safety of employees or cause undue hardship on an operator.
Section: Previous 27-1231 27-1232 27-1233 27-1234 27-1235 27-1236 27-1251 27-1252 27-1253 27-1254 27-1255 27-1271 27-1272 27-1273 27-1274 NextLast modified: October 13, 2016