45-1446. Time for determining costs; change of determination
A. The state's portion of the costs of lands, easements and rights-of-way shall be determined by the director at or prior to the time the director submits his report to the legislature recommending an appropriation for such project.
B. The state's portion of such costs shall not be changed unless there are major project changes made in the plan of improvement, in which case the director, prior to the next appropriation of state funds for the project, shall review the project and make such reports and recommendations to the legislature as he deems justified by the project changes.
Section: Previous 45-1428 45-1429 45-1441 45-1442 45-1443 45-1444 45-1445 45-1446 45-1447 45-1448 45-1449 45-1450 45-1451 45-1471 45-1473 NextLast modified: October 13, 2016