Arizona Revised Statutes § 9-554 License Required Before Construction

9-554. License required before construction

A. A new industrial gas pipeline shall not be constructed within any incorporated city or town or within the unincorporated area of a county before a license is issued as provided in this article.

B. A licensing authority may terminate a license according to its terms and conditions if a license holder is in default under the license.

Section: Previous  9-537  9-538  9-539  9-540  9-551  9-552  9-553  9-554  9-571  9-581  9-582  9-583  9-601  9-602  9-603  Next