(a) Each application submitted by an operator of an exploration and production fluid transportation system equipped for carrying or pulling a transportation tank as defined by the Oil and Gas Commission's General Rules and Regulations Rule E-3 shall be accompanied by an application fee for each transportation tank as determined by the Oil and Gas Commission in an amount not to exceed one hundred dollars ($100).
(b) Each application by a pipeline operator to construct or operate a jurisdictional pipeline system as defined by the Oil and Gas Commission's General Rules and Regulations Rule D-17 shall be accompanied by a permit fee as determined by the commission in an amount not to exceed five thousand dollars ($5,000).
(c) (1) Each application for a hearing shall be accompanied by a fee as determined by the commission in an amount up to two dollars ($2.00) for each person whose address is provided by the applicant and the applicant has identified in the application or requested to receive a copy of the order from the hearing under the Oil and Gas Commission's General Rules and Regulations Rule A-2(a)(5).
(2) Subdivision (c)(1) of this section shall not apply to an application filed by the commission.
(d) The fees collected under subsections (a), (b), and (c) of this section are cash funds of the commission to use in any manner permissible under law.
Section: Previous 15-71-104 15-71-105 15-71-106 15-71-107 15-71-108 15-71-109 15-71-110 15-71-111 15-71-112 15-71-113 15-71-114 15-71-115 15-71-116 15-71-117Last modified: November 15, 2016