(a) Every manufacturer, contractor, jobber, owner, or user of a boiler or unfired pressure vessel or pressure piping system shall obtain a permit from the Boiler Inspection Division before any boiler or unfired pressure vessel or pressure piping system may be installed or moved and installed in the State of Arkansas.
(b) When new boilers or unfired pressure vessels are to be installed, the manufacturer's data report for each boiler and unfired pressure vessel shall be submitted with the application for installation.
(c) No boiler or unfired pressure vessel or pressure piping may be installed without approval from the division.
Section: Previous 20-23-302 20-23-303 20-23-304 20-23-305 20-23-306 20-23-307 20-23-308 20-23-309 20-23-310 20-23-311 20-23-312 20-23-313 20-23-314 NextLast modified: November 15, 2016