                     Referring now to Figure 4, the next step in the erection process is the installation                 
              of panelized interior party wall elements 10 and 11 which are securely fastened to                          
              the concrete slab 2 and lower core module 1.  Panelized exterior wall element 12 is then                    
              attached to the lateral end extremities of panelized interior party wall elements 10 and                    
              11.  Figure 5 depicts the placement of panelized floor elements 13 and 14 which                             
              interlock with the lower and middle core modules 1 and 4 and span outwardly to                              
              panelized exterior wall element 12 upon which the floor elements 13 and 14 structurally                     
              bear.  Figure 5 further illustrates a pre-fabricated notch 15 in panelized floor element 13                 
              which provides head clearance above stair component 8 attached to staircase 9.  Also                        
              shown in Figure 5 is the placement of panelized interior party wall element 16 which is                     
              attached to slab 2 and lower core module 1.  A corresponding party wall element 17 (not                     
              shown in Figure 5) is attached to slab 2 and lower core module opposite wall element                        
              16.  Panelized exterior wall element 18 is then fastened to the lateral end extremities of                  
              interior party wall elements 16 and 17.                                                                     


                     Referring now to Figure 6, second floor panelized interior party wall elements 19                    
              and 20 are respectively installed upon and fastened to panelized floor elements 13                          
              and 14.  The subject wall elements 19 and 20 are similarly secured to the middle core                       
              module 4.  The next step in the erection process is the placement of second floor                           
              panelized exterior wall element 21, which is fastened on its bottom end to the upper                        