(a) Before notifying the appropriate regional notification center, an excavator planning to conduct an excavation shall delineate the area to be excavated. If the area is not delineated, an operator may, at the operator’s discretion, choose not to locate and field mark until the area to be excavated has been delineated.
(b) Except in an emergency, an excavator planning to conduct an excavation shall notify the appropriate regional notification center of the excavator’s intent to excavate at least two working days, and not more than 14 calendar days, before beginning that excavation. The date of the notification shall not count as part of the two-working-day notice. If an excavator gives less notice than the legal excavation start date and time and the excavation is not an emergency, the regional notification center will take the information and provide a ticket, but an operator has until the legal excavation start date and time to respond. However, an excavator and an operator may mutually agree to a different notice and start date. The contact information for operators notified shall be available to the excavator.
(c) When the excavation is proposed within 10 feet of a high priority subsurface installation, the operator of the high priority subsurface installation shall notify the excavator of the existence of the high priority subsurface installation to set up an onsite meeting prior to the legal excavation start date and time or at a mutually agreed upon time to determine actions or activities required to verify the location and prevent damage to the high priority subsurface installation. As part of the meeting, the excavator shall discuss with the operator the method and tools that will be used during the excavation and the information the operator will provide to assist in verifying the location of the subsurface installation. The excavator shall not begin excavating until after the completion of the onsite meeting.
(d) Except in an emergency, every excavator covered by Section 4216.8 planning to conduct an excavation on private property that does not require an excavation permit may contact the appropriate regional notification center if the private property is known, or reasonably should be known, to contain a subsurface installation other than the underground facility owned or operated by the excavator. Before notifying the appropriate regional notification center, an excavator shall delineate the area to be excavated. Any temporary marking placed at the planned excavation location shall be clearly seen, functional, and considerate to surface aesthetics and the local community. An excavator shall check if any local ordinances apply to the placement of temporary markings.
(e) The regional notification center shall provide a ticket to the person who contacts the center pursuant to this section and shall notify any member, if known, who has a subsurface installation in the area of the proposed excavation. A ticket shall be valid for 28 days from the date of issuance. If work continues beyond 28 days, the excavator shall renew the ticket either by accessing the center’s Internet Web site or by calling “811” by the end of the 28th day.
(f) A record of all notifications by an excavator or operator to the regional notification center shall be maintained for a period of not less than three years. The record shall be available for inspection by the excavator and any member, or their representative, during normal working hours and according to guidelines for inspection as may be established by the regional notification centers.
(g) Unless an emergency exists, an excavator shall not begin excavation until the excavator receives a response from all known operators of subsurface installations within the delineated boundaries of the proposed area of excavation pursuant to subdivision (a) of Section 4216.3 and until the completion of any onsite meeting, if required by subdivision (c).
(h) If a site requires special access, an excavator shall request an operator to contact the excavator regarding that special access or give special instructions on the location request.
(i) If a ticket obtained by an excavator expires but work is ongoing, the excavator shall contact the regional notification center and get a new ticket and wait a minimum of two working days, not including the date of the contact, before restarting excavation. All excavation shall cease during the waiting period.
(Amended by Stats. 2017, Ch. 26, Sec. 46. (SB 92) Effective June 27, 2017.)
Last modified: October 25, 2018