(a) (1) Section 28 of Chapter 7 of the Statutes of 2007 contains an appropriation of three hundred million dollars ($300,000,000) for capital outlay to be allocated to renovate, improve, or expand infrastructure capacity at existing prison facilities. The funds appropriated by that section may be used for land acquisition, environmental services, architectural programming, engineering assessments, schematic design, preliminary plans, working drawings, and construction.
(2) These funds may also be used to address deficiencies related to utility systems owned by local government entities and serving state prison facilities subject to the provisions of Section 54999 of the Government Code. The department shall report on any funds to be expended for this purpose to the Joint Legislative Budget Committee. If the committee fails to take any action with respect to each notification within 20 days after submittal, this inaction shall be deemed to be approval for purposes of this section.
(3) These funds may also be used for the design and construction of improvements to dental facilities at state prison facilities.
(4) These funds may also be used for the design and construction of improvements to medication distribution facilities at state prison facilities.
(5) These funds may also be used for the design and construction of projects in the Health Care Facility Improvement Program at state prison facilities.
(6) This subdivision authorizes the scope and cost of a single capital outlay project for purposes of calculating augmentations pursuant to Section 13332.11 or 13332.19.
(b) The scope and costs of the projects described in subdivision (a) of this section shall be subject to approval and administrative oversight by the State Public Works Board, including augmentations, pursuant to Section 13332.11 or 13332.19 of the Government Code. The availability of an augmentation for each individual project allocation shall be based on the total applicable capital outlay appropriation contained in Section 28 of Chapter 7 of the Statutes of 2007 and is not limited to 20 percent of the individual project allocation. These requirements shall be applied separately to each institution. All of the necessary infrastructure improvements at each institution may be treated as one project such that there would be one infrastructure improvement project at each institution. The scope and cost of each infrastructure improvement project shall be established by the board individually. The amount of the total appropriation in Section 28 of Chapter 7 of the Statutes of 2007 that is necessary for each infrastructure improvement project shall be allocated by institution. The appropriation may be allocated based on current estimates. These initial allocations may be adjusted commensurate to changes that occur during the progression of the projects. As allocations are made or adjusted, the anticipated deficit or savings shall be continuously tracked and reported. Once the total appropriation has been allocated, any augmentation necessary to fund an anticipated deficit shall be based on the total appropriation and allocated to each project as necessary. Concurrent with the request to the board to establish each project authorized pursuant to this section, the Department of Corrections and Rehabilitation shall report the associated scope, cost, and schedule information to the Joint Legislative Budget Committee.
(c) The projects authorized pursuant to this section shall be part of the Department of Corrections and Rehabilitation’s master plan, as defined in Section 7000.
(d) The reporting requirements set forth in Sections 7000 to 7003.5, inclusive, shall apply separately to each project authorized pursuant to this section.
(Amended by Stats. 2014, Ch. 26, Sec. 35. (AB 1468) Effective June 20, 2014.)
Last modified: October 25, 2018