California Public Contract Code ARTICLE 8 - Modifications; Performance; Payment

  • Section 10250.
    The department may increase or decrease quantities of work to be done under a unit basis contract during the progress of the work.(Enacted by Stats....
  • Section 10251.
    The department may cause the insertion of provisions in any contract for the performance of such extra work and the furnishing of materials therefor by...
  • Section 10252.
    The director may grant such extensions of time for completion as he deems for the best interests of the state.(Enacted by Stats. 1981, Ch. 306.)
  • Section 10253.
    If the director deems that a contractor has failed to supply an adequate working force, or material of proper quality, or has failed to comply...
  • Section 10254.
    If the defaults are not remedied within the time specified in the notice, the contractor’s control shall terminate as of the expiration of that time.(Enacted...
  • Section 10255.
    Upon such termination, the director may take possession of and use all or any part of the contractor’s materials, tools, equipment, and appliances upon the...
  • Section 10256.
    Such informal contracts may be awarded only after a proposal form has been prepared, a copy is served upon the contractor whose control has been...
  • Section 10257.
    The provisions of this part, except as to prequalification, are not applicable to the award of informal contracts.(Enacted by Stats. 1981, Ch. 306.)
  • Section 10258.
    If the control of a contractor is terminated or he abandons the work, and the work is performed by day’s labor or informal contract as...
  • Section 10259.
    On the completion of the contract, the original contractor is entitled to the return of all his unused materials, and his equipment, tools, and appliances,...
  • Section 10260.
    The notices required by this article may be served on the contractor or on his agent having charge of the work, personally, or by registered...
  • Section 10261.
    (a) Payments upon contracts shall be made as the department prescribes upon estimates made and approved by the department, but progress payments shall not be made...
  • Section 10261.a.
    (a) On and after January 1, 2023, payments upon contracts shall be made as the department prescribes upon estimates made and approved by the department, but...
  • Section 10261.5.
    (a) Any state agency which fails to make any progress payment within 30 days after receipt of the payment request from a contractor on a construction...
  • Section 10261.7.
    (a) Within 10 days of making a construction contract payment, a state agency that maintains an Internet Web site shall post on its Internet Web site...
  • Section 10262.
    The contractor shall pay to his or her subcontractors, within seven days of receipt of each progress payment, the respective amounts allowed the contractor on...
  • Section 10262.3.
    To facilitate enforcement of Section 10262, the Department of General Services shall publish in the California State Contracts Register notice of progress payments made to...
  • Section 10262.5.
    (a) Notwithstanding any other law, a prime contractor or subcontractor shall pay to any subcontractor, not later than seven days after receipt of each progress payment,...
  • Section 10263.
    (a) Provisions shall be included in any invitation for bid and in any contract documents to permit the substitution of securities for any moneys withheld by...
  • Section 10264.
    (a) With the exception of projects over water requiring marine access, and which have a contract amount greater than twenty-five million dollars ($25,000,000), in addition to...
  • Section 10265.
    A claim pursuant to Part 3 (commencing with Section 900) of Division 3.6 of Title 1 of the Government Code is not required, but legal...