(a) (1) On or before March 1, 2012, the commission shall open a proceeding to determine appropriate targets, if any, for each load-serving entity to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. As part of this proceeding, the commission may consider a variety of possible policies to encourage the cost-effective deployment of energy storage systems, including refinement of existing procurement methods to properly value energy storage systems.
(2) The commission shall adopt the procurement targets, if determined to be appropriate pursuant to paragraph (1), by October 1, 2013.
(3) The commission shall reevaluate the determinations made pursuant to this subdivision not less than once every three years.
(4) Nothing in this section prohibits the commission’s evaluation and approval of any application for funding or recovery of costs of any ongoing or new development, trialing, and testing of energy storage projects or technologies outside of the proceeding required by this chapter.
(b) (1) On or before March 1, 2012, the governing board of each local publicly owned electric utility shall initiate a process to determine appropriate targets, if any, for the utility to procure viable and cost-effective energy storage systems to be achieved by December 31, 2016, and December 31, 2020. As part of this proceeding, the governing board may consider a variety of possible policies to encourage the cost-effective deployment of energy storage systems, including refinement of existing procurement methods to properly value energy storage systems.
(2) The governing board shall adopt the procurement targets, if determined to be appropriate pursuant to paragraph (1), by October 1, 2014.
(3) The governing board shall reevaluate the determinations made pursuant to this subdivision not less than once every three years.
(Amended by Stats. 2012, Ch. 606, Sec. 9. (AB 2227) Effective January 1, 2013.)
Last modified: October 25, 2018