California Public Utilities Code ARTICLE 5 - Electrical and Gas Corporations
- Section 1091.
In addition to the requirements of Article 1 (commencing with Section 1001) and any other provision of law, every electrical and every gas corporation proposing...
- Section 1092.
Whenever application is made to the commission for certification of an electric or gas plant, line, or extension subject to this article, the commission shall...
- Section 1093.
(a) The construction project board of consultants shall consist of eminently qualified and highly experienced design, construction, and project management economic specialists who can, as a...
- Section 1094.
The members of the construction project board of consultants shall receive fees and expenses from the commission. The corporation whose project the construction project board...
- Section 1095.
The corporation shall provide the construction project board of consultants with all information the board determines necessary for its evaluation of the project. The corporation...
- Section 1096.
The construction project board of consultants shall evaluate the design, construction, project management, and economic soundness of the project as directed by the commission, and...
- Section 1097.
(a) For purposes of assisting the construction project board of consultants in monitoring project construction, the corporation shall submit the current design, estimate of project costs,...
- Section 1098.
Throughout the design and construction process, the corporation shall submit quarterly progress reports to the commission and the construction project board of consultants on the...
- Section 1099.
Upon completion of the project and commencement of operations, the construction project board of consultants shall submit a final report of its findings and recommendations...
- Section 1100.
The commission and the corporation shall give full consideration to all reports, findings, and recommendations of the construction project board of consultants and provide a...
- Section 1101.
No provision of this article shall be construed to relieve an electrical or gas corporation of any responsibility for the construction or modification of any...
- Section 1102.
(a) Notwithstanding any other provision of this article, and in addition to the requirements of Article 1 (commencing with Section 1001), an electrical corporation proposing to...
- Section 1103.
(a) If a new underground gas storage facility is proposed, the commission shall ensure that a risk assessment evaluating the potential impact of a leak from...
Last modified: October 22, 2018