California Public Utilities Code ARTICLE 12 - Construction Manager/General Contractor Project Delivery Contracts
- Section 103394.
For purposes of this article, the following terms shall have the following meanings:(a) “Construction Manager/General Contractor method” or “CMGC” means the Construction Manager/General Contractor method as...
- Section 103395.
(a) Subject to the limitations of this article, the district may utilize the CMGC project delivery method for public transit projects within its jurisdiction.(b) The district may...
- Section 103396.
Any public works project that is contracted for pursuant to this article shall be subject to the requirements of Section 1771.4 of the Labor Code.(Repealed...
- Section 103397.
(a) If a contract for CMGC services is entered into pursuant to this article and includes preconstruction services by the construction manager, the district shall enter...
- Section 103398.
Nothing in this article affects, expands, alters, or limits any rights or remedies otherwise available at law.(Added by Stats. 2013, Ch. 320, Sec. 2. (AB...
- Section 103399.
(a) Upon completion of a project using the CMGC project delivery method, the district shall prepare a progress report to the board of directors. The progress...
- Section 103399.1.
(a) The provisions of this article are severable. If any provision of this article or its application is held invalid, that invalidity shall not affect other...