California Public Utilities Code CHAPTER 6 - Pasadena Metro Blue Line Construction Authority
- Section 132400.
For purposes of this chapter, the following terms have the following meanings:(a) The “authority” is the Metro Gold Line Foothill Extension Construction Authority created under this...
- Section 132405.
The authority is hereby created for the purpose of awarding and overseeing all design and construction contracts for completion of the project.(Added by Stats. 1998,...
- Section 132410.
(a) The authority has all of the powers necessary for planning, acquiring, leasing, developing, jointly developing, owning, controlling, using, jointly using, disposing of, designing, procuring, and...
- Section 132415.
(a) The authority shall be governed by a board consisting of five voting members and four nonvoting members who shall be appointed as follows:(1) Three members shall...
- Section 132420.
(a) The board may appoint an executive director to serve at the pleasure of the authority.(b) The executive director is exempt from all civil service provisions and...
- Section 132425.
The LACMTA shall identify and expeditiously enter into an agreement with the authority to hold in trust with the authority all real and personal property,...
- Section 132430.
(a) The LACMTA shall transfer the unencumbered balance of all local funds programmed for completion of the project and that have been identified in the Restructuring...
- Section 132435.
The authority shall enter into a memorandum of understanding with the LACMTA that shall specifically address the ability of the LACMTA to review any significant...
- Section 132440.
The authority shall not encumber any future farebox revenue anticipated from the operation of the project.(Added by Stats. 1998, Ch. 1021, Sec. 1. Effective January...
- Section 132445.
The authority shall not encumber the project with any obligation that is transferable to the LACMTA upon completion of the design and construction of the...
- Section 132450.
(a) (1) The LACMTA shall assume responsibility for operating all completed phases of the project.(2) Subject to subparagraph (A), the LACMTA shall have the authority to operate the...