Illinois Compiled Statutes 20 ILCS 3960 Illinois Health Facilities Planning Act. Section 5

    (20 ILCS 3960/5) (from Ch. 111 1/2, par. 1155)

    (Section scheduled to be repealed on December 31, 2019)

    Sec. 5. Construction, modification, or establishment of health care facilities or acquisition of major medical equipment; permits or exemptions. No person shall construct, modify or establish a health care facility or acquire major medical equipment without first obtaining a permit or exemption from the State Board. The State Board shall not delegate to the staff of the State Board or any other person or entity the authority to grant permits or exemptions whenever the staff or other person or entity would be required to exercise any discretion affecting the decision to grant a permit or exemption. The State Board may, by rule, delegate authority to the Chairman to grant permits or exemptions when applications meet all of the State Board's review criteria and are unopposed.

    A permit or exemption shall be obtained prior to the acquisition of major medical equipment or to the construction or modification of a health care facility which:

        (a) requires a total capital expenditure in excess of

    the capital expenditure minimum; or

        (b) substantially changes the scope or changes the

    functional operation of the facility; or

        (c) changes the bed capacity of a health care

    facility by increasing the total number of beds or by distributing beds among various categories of service or by relocating beds from one physical facility or site to another by more than 20 beds or more than 10% of total bed capacity as defined by the State Board, whichever is less, over a 2 year period.

    A permit shall be valid only for the defined construction or modifications, site, amount and person named in the application for such permit and shall not be transferable or assignable. A permit shall be valid until such time as the project has been completed, provided that the project commences and proceeds to completion with due diligence by the completion date or extension date approved by the Board.

    A permit holder must do the following: (i) submit the final completion and cost report for the project within 90 days after the approved project completion date or extension date and (ii) submit annual progress reports no earlier than 30 days before and no later than 30 days after each anniversary date of the Board's approval of the permit until the project is completed. To maintain a valid permit and to monitor progress toward project commencement and completion, routine post-permit reports shall be limited to annual progress reports and the final completion and cost report. Annual progress reports shall include information regarding the committed funds expended toward the approved project. If the project is not completed in one year, then, by the second annual report, the permit holder shall expend 33% or more of the total project cost or shall make a commitment to expend 33% or more of the total project cost by signed contracts or other legal means, and the report shall contain information regarding those expenditures or commitments. If the project is to be completed in one year, then the first annual report shall contain the expenditure commitment information for the total project cost. The State Board may extend the expenditure commitment period after considering a permit holder's showing of good cause and request for additional time to complete the project.

    The Certificate of Need process required under this Act is designed to restrain rising health care costs by preventing unnecessary construction or modification of health care facilities. The Board must assure that the establishment, construction, or modification of a health care facility or the acquisition of major medical equipment is consistent with the public interest and that the proposed project is consistent with the orderly and economic development or acquisition of those facilities and equipment and is in accord with the standards, criteria, or plans of need adopted and approved by the Board. Board decisions regarding the construction of health care facilities must consider capacity, quality, value, and equity. Projects may deviate from the costs, fees, and expenses provided in their project cost information for the project's cost components, provided that the final total project cost does not exceed the approved permit amount. Project alterations shall not increase the total approved permit amount by more than the limit set forth under the Board's rules.

    Major construction projects, for the purposes of this Act, shall include but are not limited to: projects for the construction of new buildings; additions to existing facilities; modernization projects whose cost is in excess of $1,000,000 or 10% of the facilities' operating revenue, whichever is less; and such other projects as the State Board shall define and prescribe pursuant to this Act.

    The acquisition by any person of major medical equipment that will not be owned by or located in a health care facility and that will not be used to provide services to inpatients of a health care facility shall be exempt from review provided that a notice is filed in accordance with exemption requirements.

    Notwithstanding any other provision of this Act, no permit or exemption is required for the construction or modification of a non-clinical service area of a health care facility.

(Source: P.A. 97-1115, eff. 8-27-12; 98-414, eff. 1-1-14.)