    Sec. 8-104. Natural gas energy efficiency programs.

    (a) It is the policy of the State that natural gas utilities and the Department of Commerce and Economic Opportunity are required to use cost-effective energy efficiency to reduce direct and indirect costs to consumers. It serves the public interest to allow natural gas utilities to recover costs for reasonably and prudently incurred expenses for cost-effective energy efficiency measures.

    (b) For purposes of this Section, "energy efficiency" means measures that reduce the amount of energy required to achieve a given end use. "Energy efficiency" also includes measures that reduce the total Btus of electricity and natural gas needed to meet the end use or uses. "Cost-effective" means that the measures satisfy the total resource cost test which, for purposes of this Section, means a standard that is met if, for an investment in energy efficiency, the benefit-cost ratio is greater than one. The benefit-cost ratio is the ratio of the net present value of the total benefits of the measures to the net present value of the total costs as calculated over the lifetime of the measures. The total resource cost test compares the sum of avoided natural gas utility costs, representing the benefits that accrue to the system and the participant in the delivery of those efficiency measures, as well as other quantifiable societal benefits, including avoided electric utility costs, to the sum of all incremental costs of end use measures (including both utility and participant contributions), plus costs to administer, deliver, and evaluate each demand-side measure, to quantify the net savings obtained by substituting demand-side measures for supply resources. In calculating avoided costs, reasonable estimates shall be included for financial costs likely to be imposed by future regulation of emissions of greenhouse gases. The low-income programs described in item (4) of subsection (f) of this Section shall not be required to meet the total resource cost test.

    (c) Natural gas utilities shall implement cost-effective energy efficiency measures to meet at least the following natural gas savings requirements, which shall be based upon the total amount of gas delivered to retail customers, other than the customers described in subsection (m) of this Section, during calendar year 2009 multiplied by the applicable percentage. Natural gas utilities may comply with this Section by meeting the annual incremental savings goal in the applicable year or by showing that total cumulative annual savings within a 3-year planning period associated with measures implemented after May 31, 2011 were equal to the sum of each annual incremental savings requirement from May 31, 2011 through the end of the applicable year:

        (1) 0.2% by May 31, 2012;

        (2) an additional 0.4% by May 31, 2013, increasing

    total savings to .6%;

        (3) an additional 0.6% by May 31, 2014, increasing

    total savings to 1.2%;

        (4) an additional 0.8% by May 31, 2015, increasing

    total savings to 2.0%;

        (5) an additional 1% by May 31, 2016, increasing

    total savings to 3.0%;

        (6) an additional 1.2% by May 31, 2017, increasing

    total savings to 4.2%;

        (7) an additional 1.4% by May 31, 2018, increasing

    total savings to 5.6%;

        (8) an additional 1.5% by May 31, 2019, increasing

    total savings to 7.1%; and

        (9) an additional 1.5% in each 12-month period

    thereafter.

    (d) Notwithstanding the requirements of subsection (c) of this Section, a natural gas utility shall limit the amount of energy efficiency implemented in any 3-year reporting period established by subsection (f) of Section 8-104 of this Act, by an amount necessary to limit the estimated average increase in the amounts paid by retail customers in connection with natural gas service to no more than 2% in the applicable 3-year reporting period. The energy savings requirements in subsection (c) of this Section may be reduced by the Commission for the subject plan, if the utility demonstrates by substantial evidence that it is highly unlikely that the requirements could be achieved without exceeding the applicable spending limits in any 3-year reporting period. No later than September 1, 2013, the Commission shall review the limitation on the amount of energy efficiency measures implemented pursuant to this Section and report to the General Assembly, in the report required by subsection (k) of this Section, its findings as to whether that limitation unduly constrains the procurement of energy efficiency measures.

    (e) Natural gas utilities shall be responsible for overseeing the design, development, and filing of their efficiency plans with the Commission. The utility shall utilize 75% of the available funding associated with energy efficiency programs approved by the Commission, and may outsource various aspects of program development and implementation. The remaining 25% of available funding shall be used by the Department of Commerce and Economic Opportunity to implement energy efficiency measures that achieve no less than 20% of the requirements of subsection (c) of this Section. Such measures shall be designed in conjunction with the utility and approved by the Commission. The Department may outsource development and implementation of energy efficiency measures. A minimum of 10% of the entire portfolio of cost-effective energy efficiency measures shall be procured from local government, municipal corporations, school districts, and community college districts. Five percent of the entire portfolio of cost-effective energy efficiency measures may be granted to local government and municipal corporations for market transformation initiatives. The Department shall coordinate the implementation of these measures and shall integrate delivery of natural gas efficiency programs with electric efficiency programs delivered pursuant to Section 8-103 of this Act, unless the Department can show that integration is not feasible.

    The apportionment of the dollars to cover the costs to implement the Department's share of the portfolio of energy efficiency measures shall be made to the Department once the Department has executed rebate agreements, grants, or contracts for energy efficiency measures and provided supporting documentation for those rebate agreements, grants, and contracts to the utility. The Department is authorized to adopt any rules necessary and prescribe procedures in order to ensure compliance by applicants in carrying out the purposes of rebate agreements for energy efficiency measures implemented by the Department made under this Section.

    The details of the measures implemented by the Department shall be submitted by the Department to the Commission in connection with the utility's filing regarding the energy efficiency measures that the utility implements.

    A utility providing approved energy efficiency measures in this State shall be permitted to recover costs of those measures through an automatic adjustment clause tariff filed with and approved by the Commission. The tariff shall be established outside the context of a general rate case and shall be applicable to the utility's customers other than the customers described in subsection (m) of this Section. Each year the Commission shall initiate a review to reconcile any amounts collected with the actual costs and to determine the required adjustment to the annual tariff factor to match annual expenditures.

    Each utility shall include, in its recovery of costs, the costs estimated for both the utility's and the Department's implementation of energy efficiency measures. Costs collected by the utility for measures implemented by the Department shall be submitted to the Department pursuant to Section 605-323 of the Civil Administrative Code of Illinois, shall be deposited into the Energy Efficiency Portfolio Standards Fund, and shall be used by the Department solely for the purpose of implementing these measures. A utility shall not be required to advance any moneys to the Department but only to forward such funds as it has collected. The Department shall report to the Commission on an annual basis regarding the costs actually incurred by the Department in the implementation of the measures. Any changes to the costs of energy efficiency measures as a result of plan modifications shall be appropriately reflected in amounts recovered by the utility and turned over to the Department.

    The portfolio of measures, administered by both the utilities and the Department, shall, in combination, be designed to achieve the annual energy savings requirements set forth in subsection (c) of this Section, as modified by subsection (d) of this Section.

    The utility and the Department shall agree upon a reasonable portfolio of measures and determine the measurable corresponding percentage of the savings goals associated with measures implemented by the Department.

    No utility shall be assessed a penalty under subsection (f) of this Section for failure to make a timely filing if that failure is the result of a lack of agreement with the Department with respect to the allocation of responsibilities or related costs or target assignments. In that case, the Department and the utility shall file their respective plans with the Commission and the Commission shall determine an appropriate division of measures and programs that meets the requirements of this Section.

    If the Department is unable to meet performance requirements for the portion of the portfolio implemented by the Department, then the utility and the Department shall jointly submit a modified filing to the Commission explaining the performance shortfall and recommending an appropriate course going forward, including any program modifications that may be appropriate in light of the evaluations conducted under item (8) of subsection (f) of this Section. In this case, the utility obligation to collect the Department's costs and turn over those funds to the Department under this subsection (e) shall continue only if the Commission approves the modifications to the plan proposed by the Department.

    (f) No later than October 1, 2010, each gas utility shall file an energy efficiency plan with the Commission to meet the energy efficiency standards through May 31, 2014. Every 3 years thereafter, each utility shall file, no later than October 1, an energy efficiency plan with the Commission. If a utility does not file such a plan by October 1 of the applicable year, then it shall face a penalty of $100,000 per day until the plan is filed. Each utility's plan shall set forth the utility's proposals to meet the utility's portion of the energy efficiency standards identified in subsection (c) of this Section, as modified by subsection (d) of this Section, taking into account the unique circumstances of the utility's service territory. The Commission shall seek public comment on the utility's plan and shall issue an order approving or disapproving each plan. If the Commission disapproves a plan, the Commission shall, within 30 days, describe in detail the reasons for the disapproval and describe a path by which the utility may file a revised draft of the plan to address the Commission's concerns satisfactorily. If the utility does not refile with the Commission within 60 days after the disapproval, the utility shall be subject to penalties at a rate of $100,000 per day until the plan is filed. This process shall continue, and penalties shall accrue, until the utility has successfully filed a portfolio of energy efficiency measures. Penalties shall be deposited into the Energy Efficiency Trust Fund and the cost of any such penalties may not be recovered from ratepayers. In submitting proposed energy efficiency plans and funding levels to meet the savings goals adopted by this Act the utility shall:

        (1) Demonstrate that its proposed energy efficiency

    measures will achieve the requirements that are identified in subsection (c) of this Section, as modified by subsection (d) of this Section.

        (2) Present specific proposals to implement new

    building and appliance standards that have been placed into effect.

        (3) Present estimates of the total amount paid for

    gas service expressed on a per therm basis associated with the proposed portfolio of measures designed to meet the requirements that are identified in subsection (c) of this Section, as modified by subsection (d) of this Section.

        (4) Coordinate with the Department to present a

    portfolio of energy efficiency measures proportionate to the share of total annual utility revenues in Illinois from households at or below 150% of the poverty level. Such programs shall be targeted to households with incomes at or below 80% of area median income.

        (5) Demonstrate that its overall portfolio of energy

    efficiency measures, not including programs covered by item (4) of this subsection (f), are cost-effective using the total resource cost test and represent a diverse cross section of opportunities for customers of all rate classes to participate in the programs.

        (6) Demonstrate that a gas utility affiliated with an

    electric utility that is required to comply with Section 8-103 of this Act has integrated gas and electric efficiency measures into a single program that reduces program or participant costs and appropriately allocates costs to gas and electric ratepayers. The Department shall integrate all gas and electric programs it delivers in any such utilities' service territories, unless the Department can show that integration is not feasible or appropriate.

        (7) Include a proposed cost recovery tariff mechanism

    to fund the proposed energy efficiency measures and to ensure the recovery of the prudently and reasonably incurred costs of Commission-approved programs.

        (8) Provide for quarterly status reports tracking

    implementation of and expenditures for the utility's portfolio of measures and the Department's portfolio of measures, an annual independent review, and a full independent evaluation of the 3-year results of the performance and the cost-effectiveness of the utility's and Department's portfolios of measures and broader net program impacts and, to the extent practical, for adjustment of the measures on a going forward basis as a result of the evaluations. The resources dedicated to evaluation shall not exceed 3% of portfolio resources in any given 3-year period.

    (g) No more than 3% of expenditures on energy efficiency measures may be allocated for demonstration of breakthrough equipment and devices.

    (h) Illinois natural gas utilities that are affiliated by virtue of a common parent company may, at the utilities' request, be considered a single natural gas utility for purposes of complying with this Section.

    (i) If, after 3 years, a gas utility fails to meet the efficiency standard specified in subsection (c) of this Section as modified by subsection (d), then it shall make a contribution to the Low-Income Home Energy Assistance Program. The total liability for failure to meet the goal shall be assessed as follows:

        (1) a large gas utility shall pay $600,000;

        (2) a medium gas utility shall pay $400,000; and

        (3) a small gas utility shall pay $200,000.

    For purposes of this Section, (i) a "large gas utility" is a gas utility that on December 31, 2008, served more than 1,500,000 gas customers in Illinois; (ii) a "medium gas utility" is a gas utility that on December 31, 2008, served fewer than 1,500,000, but more than 500,000 gas customers in Illinois; and (iii) a "small gas utility" is a gas utility that on December 31, 2008, served fewer than 500,000 and more than 100,000 gas customers in Illinois. The costs of this contribution may not be recovered from ratepayers.

    If a gas utility fails to meet the efficiency standard specified in subsection (c) of this Section, as modified by subsection (d) of this Section, in any 2 consecutive 3-year planning periods, then the responsibility for implementing the utility's energy efficiency measures shall be transferred to an independent program administrator selected by the Commission. Reasonable and prudent costs incurred by the independent program administrator to meet the efficiency standard specified in subsection (c) of this Section, as modified by subsection (d) of this Section, may be recovered from the customers of the affected gas utilities, other than customers described in subsection (m) of this Section. The utility shall provide the independent program administrator with all information and assistance necessary to perform the program administrator's duties including but not limited to customer, account, and energy usage data, and shall allow the program administrator to include inserts in customer bills. The utility may recover reasonable costs associated with any such assistance.

    (j) No utility shall be deemed to have failed to meet the energy efficiency standards to the extent any such failure is due to a failure of the Department.

    (k) Not later than January 1, 2012, the Commission shall develop and solicit public comment on a plan to foster statewide coordination and consistency between statutorily mandated natural gas and electric energy efficiency programs to reduce program or participant costs or to improve program performance. Not later than September 1, 2013, the Commission shall issue a report to the General Assembly containing its findings and recommendations.

    (l) This Section does not apply to a gas utility that on January 1, 2009, provided gas service to fewer than 100,000 customers in Illinois.

    (m) Subsections (a) through (k) of this Section do not apply to customers of a natural gas utility that have a North American Industry Classification System code number that is 22111 or any such code number beginning with the digits 31, 32, or 33 and (i) annual usage in the aggregate of 4 million therms or more within the service territory of the affected gas utility or with aggregate usage of 8 million therms or more in this State and complying with the provisions of item (l) of this subsection (m); or (ii) using natural gas as feedstock and meeting the usage requirements described in item (i) of this subsection (m), to the extent such annual feedstock usage is greater than 60% of the customer's total annual usage of natural gas.

        (1) Customers described in this subsection (m) of

    this Section shall apply, on a form approved on or before October 1, 2009 by the Department, to the Department to be designated as a self-directing customer ("SDC") or as an exempt customer using natural gas as a feedstock from which other products are made, including, but not limited to, feedstock for a hydrogen plant, on or before the 1st day of February, 2010. Thereafter, application may be made not less than 6 months before the filing date of the gas utility energy efficiency plan described in subsection (f) of this Section; however, a new customer that commences taking service from a natural gas utility after February 1, 2010 may apply to become a SDC or exempt customer up to 30 days after beginning service. Customers described in this subsection (m) that have not already been approved by the Department may apply to be designated a self-directing customer or exempt customer, on a form approved by the Department, between September 1, 2013 and September 30, 2013. Customer applications that are approved by the Department under this amendatory Act of the 98th General Assembly shall be considered to be a self-directing customer or exempt customer, as applicable, for the current 3-year planning period effective December 1, 2013. Such application shall contain the following:

            (A) the customer's certification that, at the

        time of its application, it qualifies to be a SDC or exempt customer described in this subsection (m) of this Section;

            (B) in the case of a SDC, the customer's

        certification that it has established or will establish by the beginning of the utility's 3-year planning period commencing subsequent to the application, and will maintain for accounting purposes, an energy efficiency reserve account and that the customer will accrue funds in said account to be held for the purpose of funding, in whole or in part, energy efficiency measures of the customer's choosing, which may include, but are not limited to, projects involving combined heat and power systems that use the same energy source both for the generation of electrical or mechanical power and the production of steam or another form of useful thermal energy or the use of combustible gas produced from biomass, or both;

            (C) in the case of a SDC, the customer's

        certification that annual funding levels for the energy efficiency reserve account will be equal to 2% of the customer's cost of natural gas, composed of the customer's commodity cost and the delivery service charges paid to the gas utility, or $150,000, whichever is less;

            (D) in the case of a SDC, the customer's

        certification that the required reserve account balance will be capped at 3 years' worth of accruals and that the customer may, at its option, make further deposits to the account to the extent such deposit would increase the reserve account balance above the designated cap level;

            (E) in the case of a SDC, the customer's

        certification that by October 1 of each year, beginning no sooner than October 1, 2012, the customer will report to the Department information, for the 12-month period ending May 31 of the same year, on all deposits and reductions, if any, to the reserve account during the reporting year, and to the extent deposits to the reserve account in any year are in an amount less than $150,000, the basis for such reduced deposits; reserve account balances by month; a description of energy efficiency measures undertaken by the customer and paid for in whole or in part with funds from the reserve account; an estimate of the energy saved, or to be saved, by the measure; and that the report shall include a verification by an officer or plant manager of the customer or by a registered professional engineer or certified energy efficiency trade professional that the funds withdrawn from the reserve account were used for the energy efficiency measures;

            (F) in the case of an exempt customer, the

        customer's certification of the level of gas usage as feedstock in the customer's operation in a typical year and that it will provide information establishing this level, upon request of the Department;

            (G) in the case of either an exempt customer or

        a SDC, the customer's certification that it has provided the gas utility or utilities serving the customer with a copy of the application as filed with the Department;

            (H) in the case of either an exempt customer or a

        SDC, certification of the natural gas utility or utilities serving the customer in Illinois including the natural gas utility accounts that are the subject of the application; and

            (I) in the case of either an exempt customer or a

        SDC, a verification signed by a plant manager or an authorized corporate officer attesting to the truthfulness and accuracy of the information contained in the application.

        (2) The Department shall review the application to

    determine that it contains the information described in provisions (A) through (I) of item (1) of this subsection (m), as applicable. The review shall be completed within 30 days after the date the application is filed with the Department. Absent a determination by the Department within the 30-day period, the applicant shall be considered to be a SDC or exempt customer, as applicable, for all subsequent 3-year planning periods, as of the date of filing the application described in this subsection (m). If the Department determines that the application does not contain the applicable information described in provisions (A) through (I) of item (1) of this subsection (m), it shall notify the customer, in writing, of its determination that the application does not contain the required information and identify the information that is missing, and the customer shall provide the missing information within 15 working days after the date of receipt of the Department's notification.

        (3) The Department shall have the right to audit the

    information provided in the customer's application and annual reports to ensure continued compliance with the requirements of this subsection. Based on the audit, if the Department determines the customer is no longer in compliance with the requirements of items (A) through (I) of item (1) of this subsection (m), as applicable, the Department shall notify the customer in writing of the noncompliance. The customer shall have 30 days to establish its compliance, and failing to do so, may have its status as a SDC or exempt customer revoked by the Department. The Department shall treat all information provided by any customer seeking SDC status or exemption from the provisions of this Section as strictly confidential.

        (4) Upon request, or on its own motion, the

    Commission may open an investigation, no more than once every 3 years and not before October 1, 2014, to evaluate the effectiveness of the self-directing program described in this subsection (m).

    Customers described in this subsection (m) that applied to the Department on January 3, 2013, were approved by the Department on February 13, 2013 to be a self-directing customer or exempt customer, and receive natural gas from a utility that provides gas service to at least 500,000 retail customers in Illinois and electric service to at least 1,000,000 retail customers in Illinois shall be considered to be a self-directing customer or exempt customer, as applicable, for the current 3-year planning period effective December 1, 2013.

    (n) The applicability of this Section to customers described in subsection (m) of this Section is conditioned on the existence of the SDC program. In no event will any provision of this Section apply to such customers after January 1, 2020.

(Source: P.A. 97-813, eff. 7-13-12; 97-841, eff. 7-20-12; 98-90, eff. 7-15-13; 98-225, eff. 8-9-13; 98-604, eff. 12-17-13.)

Sections:  Previous  8-101  8-101.5  8-102  8-103  8-103A  8-104  8-105  8-201  8-201.5  8-202  8-203  8-204  8-205  8-206  Next

Last modified: February 18, 2015