(430 ILCS 45/8) (from Ch. 111 1/2, par. 958)
Sec. 8. Confirmation and review of plans.
(a) Authorized employees of the Agency, the IEMA and local emergency response agencies identified under Section 5 shall have authority to enter at all reasonable times any business facility subject to this Act for the purpose of ascertaining the existence of a written Chemical Safety Contingency Plan and confirming that it is readily available for use by designated facility personnel. During the visitation of a facility, the Agency may review the contents of a plan for consistency with the provisions of subsection (b) of Section 4.
(b) The IEMA may require a business to, within 30 days, submit a copy of the Chemical Safety Contingency Plan for a facility to the Agency if any one of the following events occur:
(1) The Agency conducts an on-site review under
subsection (a) of this Section, that indicates a need for improved emergency planning and so notifies the IEMA in writing; or
(2) The IEMA receives a written statement from a
local emergency planning committee which confirms that a business has refused to participate or cooperate in the emergency planning process required under Section 303 of the federal Emergency Planning and Community Right-to-Know Act of 1986.
(c) Upon receipt of the plan, the Agency shall review the plan and prepare written findings and recommendations, including any revisions that may be necessary to improve the plan. The information shall be sent to the business, the IEMA and the local emergency planning committee. Upon receipt of the information from the Agency, the business shall consider any specified revisions and initiate appropriate follow-up action to improve the plan as expeditiously as possible. The findings and recommendations by the Agency shall be made available to the public under the Freedom of Information Act.
(d) At any time after the 120th day following the date the Agency sends the findings and recommendations to the business, the Agency may provide notice to the IEMA if there is confirmation that the business has been substantially deficient in addressing the recommended revisions.
(e) The IEMA shall review the notice and related information provided by the Agency. Following the review, the IEMA, by written notice, may require the business to revise the plan in accordance with specified terms and schedule as are necessary to improve the plan. In issuing the notice, the IEMA shall consider the nature of the facility, the potential for releases and adverse impacts, any actions already taken by the business and the technical feasibility and economic reasonableness of the revisions.
(f) Any required revision shall be binding upon the business unless, within 30 days of receipt of the notification, the business submits to the IEMA a written request for reconsideration, including the reasons and, if appropriate, any alternative proposal for improvements in the plan.
(g) Within 30 days after receipt of a request for reconsideration, the IEMA shall make a final determination in writing that affirms, rejects, or modifies the required revision of the plan. This final determination shall take effect following the 35th day after receipt by the business of notice of the determination, unless prior to that date the business files a petition for review of the decision under the Administrative Review Law.
(Source: P.A. 87-168.)