(50 ILCS 20/20.10)
(Section scheduled to be repealed on June 1, 2018)
Sec. 20.10. Small design-build projects. In any case where the total overall cost of the project is estimated to be less than $12,000,000, the Commission may combine the two-phase procedure for design-build selection described in Section 20.5 into one combined step, provided that all the requirements of evaluation are performed in accordance with Section 20.5.
This Section is repealed on June 1, 2018; provided that any design-build contracts entered into before such date or any procurement of a project under this Act commenced before such date, and the contracts resulting from those procurements, shall remain effective.
(Source: P.A. 98-299, eff. 8-9-13; reenacted by P.A. 98-619, eff. 1-7-14.)