(70 ILCS 1505/26.10-9)
Sec. 26.10-9. Small design-build projects. In any case where the total overall cost of the project is estimated to be less than $12,000,000, the Chicago Park District may combine the two-phase procedure for design-build selection described in Section 26.10-8 into one combined step, provided that all the requirements of evaluation are performed in accordance with Section 26.10-8.
(Source: P.A. 96-777, eff. 8-28-09.)
Sections: Previous 26.9 26.10 26.10-1 26.10-2 26.10-3 26.10-4 26.10-5 26.10-6 26.10-7 26.10-8 26.10-9 26.10-10 26.10-11 26.10-12 26.11 Next