Michigan Compiled Laws § 460.565 Transmission Line; Certificate Required.


460.565 Transmission line; certificate required.

Sec. 5.

An electric utility, affiliated transmission company, or independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under section 4 until the commission issues a certificate for that transmission line. Except as otherwise provided in section 9, a certificate of public convenience and necessity under this act is not required for constructing a new transmission line other than a major transmission line or for reconstructing, repairing, replacing, or improving an existing transmission line, including the addition of circuits to an existing transmission line.


History: 1995, Act 30, Imd. Eff. May 17, 1995 ;-- Am. 2004, Act 198, Imd. Eff. July 12, 2004


Section: Previous  460.561  460.562  460.563  460.564  460.565  460.566  460.567  460.568  460.569  460.570  460.571  460.572  460.573  460.574  460.575  Next