Michigan Compiled Laws § 484.3105 Use Of Public Rights-of-way; Providers Subject To Permit And Fee Requirements; Facilities Located In Public Right-of-way At Effective Date Of Act; Permit Application.


484.3105 Use of public rights-of-way; providers subject to permit and fee requirements; facilities located in public right-of-way at effective date of act; permit application.

Sec. 5.

(1) A provider using or seeking to use public rights-of-way in a metropolitan area for its telecommunication facilities shall obtain a permit under section 15 from the municipality and pay all fees required under this act. Authorizations or permits previously obtained from a municipality under section 251 of the Michigan telecommunications act, 1991 PA 179, MCL 484.2251, satisfy the permit requirement of this section.

(2) A provider asserting rights under 1883 PA 129, MCL 484.1 to 484.10, is subject to the permit and fee requirements of this act.

(3) Within 180 days from the effective date of this act, a provider with facilities located in a public right-of-way as of the effective date of this act that has not previously obtained authorization or a permit under section 251 of the Michigan telecommunications act, 1991 PA 179, MCL 484.2251, shall submit an application for a permit to each municipality in which the provider has facilities located in a public right-of-way. A provider submitting an application under this subsection is not required to pay the administrative fee required under section 6(4).

(4) The authority may, for good cause, allow a provider up to an additional 180 days to submit the application required under subsection (3).


History: 2002, Act 48, Eff. Nov. 1, 2002


Section: Previous  484.3101  484.3102  484.3103  484.3104  484.3105  484.3106  484.3107  484.3108  484.3109  484.3110  484.3111  484.3112  484.3113  484.3114  484.3115  Next