Permit required to construct utility facility; transfer of permit; exemptions; waiver of exemption.
1. A person, other than a local government, shall not commence to construct a utility facility in the State without first having obtained a permit therefor from the Commission. The replacement of an existing facility with a like facility, as determined by the Commission, does not constitute construction of a utility facility. Any facility, with respect to which a permit is required, must thereafter be constructed, operated and maintained in conformity with the permit and any terms, conditions and modifications contained therein. A permit may only be issued pursuant to NRS 704.820 to 704.900, inclusive. Any authorization relating to a utility facility granted under other laws administered by the Commission constitutes a permit under those sections if the requirements of those sections have been complied with in the proceedings leading to the granting of the authorization.
2. A permit may be transferred, subject to the approval of the Commission, to a person who agrees to comply with the terms, conditions and modifications contained therein.
3. NRS 704.820 to 704.900, inclusive, do not apply to any utility facility:
(a) For which, before July 1, 1971, an application for the approval of the facility has been made to any federal, state, regional or local governmental agency which possesses the jurisdiction to consider the matters prescribed for finding and determination in NRS 704.890;
(b) For which, before July 1, 1971, a governmental agency has approved the construction of the facility and the person has incurred indebtedness to finance all or part of the cost of the construction; or
(c) Over which an agency of the Federal Government has exclusive jurisdiction.
4. Any person intending to construct a utility facility excluded from NRS 704.820 to 704.900, inclusive, pursuant to paragraph (a) or (b) of subsection 3 may elect to waive the exclusion by delivering notice of its waiver to the Commission. NRS 704.820 to 704.900, inclusive, thereafter apply to each utility facility identified in the notice from the date of its receipt by the Commission.
Last modified: February 26, 2006