27:7-44.2. Relief of contractor from maintenance of completed section
When a section of a project under contract shall have been completed prior to the completion of the entire project, the commissioner shall have authority to relieve the contractor from the maintenance of such completed section.
L.1949, c. 176, p. 566, s. 1.
Section: Previous 27-7-39 27-7-40 27-7-41 27-7-42 27-7-43 27-7-44 27-7-44.1 27-7-44.2 27-7-44.3 27-7-44.4 27-7-44.5 27-7-44.6 27-7-44.7 27-7-44.8 27-7-44.9 Next
Last modified: October 11, 2016