New Jersey Revised Statutes § 48:3-109 - Bpu Designated As Responsible Agency.

48:3-109 BPU designated as responsible agency.

8. a. The Board of Public Utilities is designated as the agency of the State Government responsible for implementing and enforcing the provisions of P.L.2009, c.4 (C.18A:18A-4.6 et al.) and for responding to requests for assistance from public entities, including boards of education, boards of trustees of public institutions of higher education, contracting units, and public agencies, authorized to implement an energy savings improvement program pursuant to P.L.2009, c.4 (C.18A:18A-4.6 et al.).

b.The board is authorized to investigate, review and take appropriate action with respect to procurements for energy savings projects conducted by public agencies, other than State contracting agencies, pursuant to P.L.2009, c.4 (C.18A:18A-4.6 et al.).

c.The board shall take such actions as it deems necessary and appropriate, consistent with the purposes of this section, to implement and enforce the provisions of P.L.2009, c.4 (C.18A:18A-4.6 et al.). The authority granted to the board pursuant to this section to enforce compliance with P.L.2009, c.4 shall include, but not be limited to:

(1)modifying a non-conforming request for proposal and any attachment thereto, whereby the board shall provide written comments to the public entity when it chooses to modify a non-conforming request for proposal, outlining any issues and providing the opportunity for the issues to be remedied;

(2) (a) modifying or canceling a procurement by a public entity for an energy savings project, whereby the board, within 14 days of its receipt of a procurement by a public entity after the procurement award, may modify or cancel the procurement, otherwise the procurement shall be deemed approved, and (b) if modifying a procurement, the board shall provide written comments to the public entity when it chooses to do so, outlining any issues and providing the opportunity for the issues to be remedied; and

(3)withholding State and federal renewable energy and energy efficiency incentives from an energy savings project.

d.The board may grant limited exceptions to a local housing authority, established pursuant to the "Local Housing Authorities Law," P.L.1938, c.19 or the "Local Redevelopment and Housing Law," P.L.1992, c.79 (C.40A:12A-1 et al.), to use an energy performance contracting process developed by the United States Department of Housing and Urban Development for selecting an energy services company subject to United States Department of Housing and Urban Development and board review and approval. The exception shall permit such process to be followed for the selection of an energy services company, the preparation of the energy savings improvement program, the selection of energy savings projects, and third party verification requirements. All other requirements for bidding and construction shall be consistent with the provisions of P.L.2009, c.4 (C.18A:18A-4.6 et al.). This limited exception shall permit the preparation of an investment grade energy savings improvement program audit to replace the requirement for the traditional energy audit component performed in advance.

e.The board shall undertake a study of the effectiveness of energy savings improvement programs implemented pursuant to P.L.2009, c.4 (C.18A:18A-4.6 et al.). Within three years after the effective date of P.L.2012, c.55 (C.52:34-25.1 et al.), the board shall prepare a report of its study and shall provide a copy thereof to the Governor and, pursuant to section 2 of P.L.1991, c.164 (C.52:14-19.1), to the Legislature.

L.2012, c.55, s.8.


Section: Previous  48-3-102  48-3-103  48-3-104  48-3-105  48-3-106  48-3-107  48-3-108  48-3-109  48-4-1  48-4-1.2  48-4-2  48-4-2.1a  48-4-2.1b  48-4-2.1c  48-4-2.1d  Next

Last modified: October 11, 2016