The Department of Environment and Natural Resources shall track the time required to process all permit applications in the One-Stop for Certain Environmental Permits Programs established by G.S. 143B-279.12 and the Express Permit and Certification Reviews established by G.S. 143B-279.13 that are received by the Department. The processing time tracked shall include (i) the total processing time from when an initial permit application is received to issuance or denial of the permit and (ii) the processing time from when a complete permit application is received to issuance or denial of the permit. No later than March 1 of each year, the Department shall report to the Fiscal Research Division of the General Assembly and the Environmental Review Commission on the permit processing times required to be tracked pursuant to this section. (2012-187, s. 13(a).)
Sections: Previous 143B-279.10 143B-279.11 143B-279.12 143B-279.13 143B-279.14 143B-279.15 143B-279.16 143B-279.17 143B-281.1 143B-282 143B-282.1 143B-283 143B-284 143B-285 143B-285.20 Next
Last modified: March 23, 2014