Oregon Statutes - Chapter 279C - Public Contracting - Public Improvements and Related Contracts - Section 279C.310 - Limitation on contracting agency constructing public improvement.

If a contracting agency fails to adopt and apply a cost accounting system that substantially complies with the model cost accounting guidelines developed by the Oregon Department of Administrative Services pursuant to section 3, chapter 869, Oregon Laws 1979, as determined by an accountant qualified to perform audits required by ORS 297.210 and 297.405 to 297.555 (Municipal Audit Law), the contracting agency may not construct a public improvement with the contracting agency’s own equipment or personnel if the cost exceeds $5,000. [2003 c.794 §99]

Section:  Previous  279C.107  279C.110  279C.115  279C.120  279C.125  279C.300  279C.305  279C.310  279C.315  279C.320  279C.325  279C.330  279C.335  279C.340  279C.345  Next

Last modified: August 7, 2008