If a contracting agency fails to adopt and apply a cost accounting system that substantially complies with the model cost accounting guidelines developed by the Oregon Department of Administrative Services pursuant to section 3, chapter 869, Oregon Laws 1979, as determined by an accountant qualified to perform audits required by ORS 297.210 and 297.405 to 297.555 (Municipal Audit Law), the contracting agency may not construct a public improvement with the contracting agency’s own equipment or personnel if the cost exceeds $5,000. [2003 c.794 §99]
Section: Previous 279C.107 279C.110 279C.115 279C.120 279C.125 279C.300 279C.305 279C.310 279C.315 279C.320 279C.325 279C.330 279C.335 279C.340 279C.345 NextLast modified: August 7, 2008